How I Set Deck Posts, Mixed Concrete, and Installed Girders

After my deck holes were officially approved by the county inspection office, it was time to fill them and set the posts. As I did when digging the original holes and when setting fence posts last year, I started by putting a few inches of gravel in the bottom of each hole for drainage. Local deck experts recommended gravel under the concrete footings we’d pour to secure the posts. We dug the holes at least 21 inches deep, so adding 2–3 inches of gravel still kept us at the county-required 18 inches.

img 48623 1

While pouring the rocks I was surprised to see some tiny frogs hop out of the dirt. They were well-camouflaged and only revealed themselves when disturbed. I rescued them before continuing with the work.

img 48623 2

I inspected the other holes carefully and still missed one big toad at first. Fortunately I found and rescued him too, with gloved hands. Clara watched the whole rescue from inside through the sliding glass door, turning it into an impromptu nature lesson.

img 48623 3

img 48623 4

I like this photo because it captures Clara and Burger watching together — Clara explaining, “See what this is? It goes ribbit ribbit.” They were both fascinated.

img 48623 5

With the holes cleared of critters and three inches of drainage rock in each, I was ready for concrete footings. Several readers suggested pre-cast Dek-Blocks, but they aren’t allowed in our county. We can, however, use other pre-cast concrete blocks.

img 48623 6

I decided to mix my own concrete instead of using the pre-cast blocks. Pre-cast blocks would have required square 12×12-inch holes and flat bottoms to sit level; most of my holes were round and uneven, so mixed concrete would fill each hole’s shape and level itself. Plus, concrete arrived with my lumber order from 84 Lumber, so it made sense to use it.

img 48623 7

To mix concrete I opened each 60 lb bag into a wheelbarrow and added water until I reached a creamy, workable consistency. I stirred the mix with a garden hoe — a humble but effective tool.

img 48623 8

img 48623 9

The first batch was a bit soupy, so I used slightly less water on later mixes. Even the wetter batch set up fine and naturally leveled at the top, which is ideal for setting posts.

img 48623 10

Mixing and pouring concrete was straightforward but grueling because of a heat advisory that warned against sustained outdoor labor. I stuck to shaded areas where I could and drank plenty of fluids, but working in intense heat was exhausting.

img 48623 11

img 48623 12

By the time all 12 holes had roughly eight inches of concrete in them I was too hot to take more photos. I snapped a picture later that evening once the sun had eased off.

img 48623 13

The next day my extra materials from 84 Lumber arrived: the 4×4 posts I needed after the county required a revised plan with more posts and girders. These 12-foot posts allowed me to get three posts out of each piece, which was handy.

img 48623 14

img 48623 15

I staggered post lengths because the ground slopes away from the house. These posts will support the 2×10 girder boards that run the long direction under the deck; the joists span the short direction and rest on those girders. The joists also need to line up with the rim boards already attached to the house for stability.

img 48623 17

Before installing posts I set up temporary joists and tied nylon string between the ends to represent the top of the girders where the joists will sit. The string is an easy way to get accurate height and alignment without holding an 18-foot 2×10 in place.

img 48623 18

With the string taut, I placed a post in a hole, leveled it with a post level, and marked where the string hit the post — that indicated where the top of the girder would be. Our county allows either metal post brackets or notching the post to accept the girder; I chose to notch the posts for a more secure fit and because it matched examples I’d seen.

img 48623 19

img 48623 20

I used a reciprocating saw to cut the notches, then placed the posts back and used stakes to hold them perfectly vertical. To secure the posts long term I used Quikrete no-mix concrete in the holes — pour in the dry powder, add water, and it soaks in and hardens. It’s much easier than mixing full batches and is county-approved for post setting.

img 48623 21

img 48623 23

After repeating the string-mark-notch-stake-cement process for the other posts on that end — a couple of hours of work in very hot weather — I left the cement to cure.

img 48623 28

On girder day I lifted an 18-foot 2×10 into the notches and clamped it to the notched post, using a sawhorse to support the other end. This allowed me to mark and notch the middle post accurately. The weight of the girder helped hold posts in place so I could set and cement them without excessive bracing.

img 48623 29

img 48623 30

One side of the deck had its three girders temporarily secured, and the opposite side required two girders that would meet at the middle post because the span was 21 feet. I temporarily set another joist across the middle for height reference and continued the same process to mark, notch, and set posts.

img 48623 33

img 48623 34

Clara remained an enthusiastic spectator throughout, even bringing an octopus balloon to watch. By the end of the afternoon all six posts were set in concrete and all girders were temporarily in place. The girders will be doubled up eventually, which will require an extra pair of hands — so I’m waiting for my dad to help with that step.

img 48623 35

img 48623 37

After doubling the girders, I’ll add two more posts and another girder to create the angled edge at the end of the deck. For now, seeing those girders in place is a big visual milestone: once the joists go in, decking boards will follow and the structure will start to really look like a finished deck.

img 48623 38

It’s been a productive stretch of DIY work in hot weather, and I’m excited for the next steps. Are you working on any outdoor projects right now — braving the heat to get them done, or taking it easier with a beach day?