How to Tile and Grout an Outdoor Patio Step-by-Step
How We Tiled and Grouted an Outdoor Sunroom Floor: DIY Process, Problems, Budget & Time Breakdown
Earlier this month we tackled tiling the sunroom floor, and after battles with cold and rain it finally feels mostly finished. The grout may look light in some photos, but we chose a charcoal-gray color — more on that later.

We’re very happy with the final result compared with the stained concrete that was there before. (We originally considered paint or stain but decided to tile — you can read more about those early decisions in our prep post.) The path from demo to finished floor had a few unexpected speed bumps, so here’s a concise walkthrough of what we did, the problems we ran into, and a full budget and time breakdown.

On October 4th I had finished leveling the floor with self-leveling concrete and was ready to start laying tile. We used large porcelain tiles that mimic slate. For installation we mixed mortar powder with a liquid admixture to create thinset. Because of the tile size I mixed large batches and used a paddle mixer and a big bucket.

I spread thinset with a flat trowel until smooth, then used the notched side at a 45-degree angle to create even grooves. For these large tiles a 1/2″ notched trowel was ideal. We used small 1/8″ spacers to keep thin grout lines suitable for an outdoor environment.

Keeping the large tiles level was one of the main challenges. Each tile touched six others in our brick-layer pattern, so achieving a flush surface took patience and adjustments. When a corner needed to sit higher I “back buttered” the tile — applying more thinset to the back — to raise it slightly and keep everything even.

The first day of tiling moved slowly thanks to leveling, mixing batch after batch, carrying tile from the garage, and making cuts on the wet saw. I finished the rest the next day, working from morning into the evening. Two people would speed things up, but I worked solo while my partner dealt with all-day morning sickness.

We like the porcelain’s slate-like appearance and textured surface — it’s less slippery when wet than smooth concrete and complements the deck. We also added a tile border to elevate the look.

After tiling, a week of rain revealed dried thinset splotches across the tiles that hadn’t been obvious while they were wet. The tile’s texture trapped thinset and the wet thinset color blended into the tile, so the dried residue looked like large spots.

Cleaning required a 50/50 water and vinegar solution to remove haze, plus a combination of scraping with a screwdriver, rubbing with vinegar-dampened cheesecloth, and scrubbing with a nylon brush to lift stubborn dry thinset. It was tedious and required elbow grease, but testing techniques on an inconspicuous tile first helped avoid damage.

After cleaning, we had to wait for the tile to be completely dry for three days before grouting. Then a cold snap delayed grouting because the grout manufacturer recommended applying grout only above 50°F. Once conditions permitted, we moved forward with grouting.

We used the following for grouting:
- Sanded grout in a charcoal color
- Flexible grout admixture
- Bucket and trowel for mixing
- Grout float for spreading
- Sponges and water for cleanup
- Towels and paper towels to keep the area tidy

Because the thinset was substantial, the grout was only needed for the narrow joints. I mixed small batches so they wouldn’t stiffen in the bucket and used a hand trowel rather than a paddle mixer. Although 1/8″ gaps could allow non-sanded grout, our tile supplier recommended sanded grout for outdoor durability.

Grouting felt satisfying and straightforward. I pressed grout into the joints with a float, scraped off excess, then smoothed joints with a slightly damp sponge. Wiping was repetitive — grout will spread if you aren’t careful — so I refreshed water frequently. The whole grouting step took about three hours.

A post-grout haze appeared as it dried. A later pass with a damp sponge and towels reduced haze significantly and showed the true charcoal grout color more accurately. We’ll let the grout cure fully before any additional rinsing to avoid permanently lightening the color.

We’ve read a few remedies for lingering haze — another vinegar rinse or a grout sealer/colorant if needed — and will decide after the grout cures. Overall, it feels great to have the floor essentially complete.

Remaining tasks in the room include boxing in exposed wires, installing sconces on the columns, addressing an old intercom, and adding outdoor-grade furniture. Even so, this is the closest the room has looked to finished since we started in August.

Here’s the budget breakdown so far:
- Wood to finish raw sides where sliding doors were removed: $194
- Contractor to remove ceiling beams: $200
- Electrician to move wires and create two fan fixture boxes: $318
- Tongue-and-groove planks for ceiling: $297
- Plywood to fill large triangles on either end: $85
- Trim, paint, primer and caulk: $197
- Fans and downrods: $260
- Self-leveling cement and supplies: $150
- Tile: $680
- Thinset, grout and other tiling supplies: $490
- Total: $2,871
That total is significant, but replacing the old extra-wide sliding doors alone would have cost around $3,200, before ceiling and floor work. We chose to do the job properly rather than take short-term shortcuts, so some expenses were necessary to get the durable, finished result we wanted.

Time-wise, here’s a rough tally of hours spent over the last two and a half months:
- Removing old sliding doors: 5 hours
- Trimming and caulking openings: 3 hours
- Demo-ing the ceiling: 3 hours
- Coordinating with contractor and electrician: 1.5 hours
- Adding triangle panels and trim (two trips): 6 hours
- Priming, painting, installing and caulking the ceiling: 21 hours
- Installing fans: 1.5 hours
- Prepping floor (scrubbing, self-leveler, planning pattern): 2 hours
- Tiling, cleaning and grouting the floor: 26 hours
- Total: ~69 hours

Those hours include physical labor, cleanup, and the learning curve for tiling a textured outdoor floor. Despite the time and occasional frustration—especially the thinset cleanup—the outcome has been worth it. Even our kiddo loves the new space.

A few final details people asked about: we installed metal edging by setting the pieces in place, embedding them with thinset, and then laying the border tile over them. The edging is aesthetic and provides a clean finish; it doesn’t hold the tile in place (thinset does). Removing the old metal door sliders lowered the transition between deck and sunroom slightly, and although the floor level varies a bit around the perimeter, we haven’t had any tripping incidents since opening the room.

We’re calling the sunroom conversion wrapped for the season. Cooler weather and a finite budget mean furniture and final touches will wait, but we’re thrilled with how the tiling project turned out. If you’re working on an outdoor tiling project, plan for weather delays, protect tiles from thinset residue while working, and test cleaning methods on a small area before tackling the whole floor.
What projects are you hoping to finish before winter? Have weather or other issues delayed your plans? We’d love to hear about your experiences.