After excitedly announcing “the hardwood floors are done!” right before moving in, we had a lot of requests for a follow-up with more detail about the tricky parts: transitions, cutting boards shorter or thinner, handling the top of the stairs, and how long everything actually took. So here’s a closer look at our hardwood floor installation process, lessons learned, and the small tasks that can eat up a lot of time.

Note: Some days were short and tackled solo, while others were long with two of us working. Use this timeline as a general guide: four hands are faster than two.
The entire floor-laying process took us about six days from placing the first board to nailing the final strip of quarter round. Sherry helped some days, but other days it was just me while she stayed back at the old house with Clara to keep her out of the sawdust. Even with previous experience, we found the project involved many smaller tasks beyond laying boards—things we’d mentally minimized before but that still required time and attention.

Getting Floors Clean: A clean subfloor is vital for a successful hardwood installation. We swept and vacuumed each room thoroughly before Day 1, and kept re-cleaning as we moved between rooms since cutting and fitting creates a lot of dust. Keeping the subfloor free of debris helps boards sit flat and prevents squeaks or uneven spots later.

Removing Baseboards: We removed baseboards ahead of the install. A utility knife scored the paint seam, and a crowbar popped the baseboards off with minimal damage. It’s a simple step, but multiplied across four bedrooms and a long hallway it takes time.

Removing Old Nails: Because we planned to reuse our baseboards, we removed old nails instead of driving them through the front and risking paint damage. Our Dremel with a metal-cutting bit trimmed the nails flush without marring the face of the trim.

Cutting Door Jambs: The Dremel was also essential for trimming door trim and jambs—about 12 of them—so the flooring could slide under for a seamless transition between rooms. I set the cutting depth using a scrap board and a piece of underlayment as a guide, and kept a scrap of paper to protect surfaces if needed.

Moving Heavy Boxes: Our flooring boxes were stored in the dining room, so every hour or two we hauled a few more boxes up the stairs to the current work area. Boxes were heavy (about 60 lbs each), and color can vary slightly between boxes, so we always grabbed planks from three different boxes at a time to keep a natural variation across the floor.

Cutting Boards Shorter: At the end of rows we used a miter saw to trim boards for quick, straight cuts. When possible we cut end pieces for multiple rows at once to save time. Since baseboards and quarter round cover the ends, these cuts just needed to be accurate enough to leave the manufacturer’s recommended expansion gap hidden behind the trim.

The expansion gap is important: if a board is cut too short the gap will peek out from under the trim, and if it’s too long it could expand later and cause buckling. We stayed within the manufacturer’s guidelines to avoid issues down the line.

Ripping Boards Thinner: For the last row in a room we often had to rip boards lengthwise so they fit flush against the wall. A table saw makes long rips easy and accurate. As with end cuts, we left the recommended expansion gap and planned to hide the ripped edge behind baseboard and quarter round.

Managing the Mess: Cutting created lots of sawdust, scraps, and empty boxes. We designated our spare room as a cutting station, so we didn’t have to climb stairs every time we needed to make a cut. That room needed a good cleanup before we finished it on Day 6—another reminder to factor cleanup time into your schedule.

Reinstalling Trim: By Day 5 most rooms were done, so I started reinstalling baseboards and adding new quarter round to clear piles of trim out of the way. A nail gun sped up reattaching the painted baseboards, but measuring and cutting quarter round took longer than I expected. Re-caulking seams and doing light touch-up paint, however, was quick and satisfying—those final details make the rooms feel finished.

Angles and Math: We have an angled wall in the hallway, which required accurate angle cuts for boards and quarter round. A basic calculator, a scrap piece of paper, and a little ninth-grade geometry helped get the angles right. If you encounter angled walls, measure twice and cut carefully.

Touching Up Trim: Removing and reinstalling baseboards caused a few dings, but a quick round of caulk and touch-up paint cleaned them up. If your trim is already painted, caulking and paint touch-ups are a relatively small part of the final finish.

Adding Transitions: Transitions are where the new hardwood meets another floor surface. We had to add one at the top of the stairs. Following advice from the flooring professionals, we removed the old bullnose and installed a matching bullnose piece for the new floor with adhesive and a couple of finish nails from the nail gun. It’s not a perfect color match to the existing stair oak, but it’s close and reads better in real life than in photos.

Once the bullnose at the top of the stairs was in place, the flooring project was officially complete. Then we dove into packing and moving—because DIY projects don’t always come with rest days. If you’re planning hardwood installation, expect unexpected small tasks: cutting jambs, ripping boards, dealing with dust, reattaching trim, and fitting transitions all add time beyond the actual board-laying.