Bathroom and Closet Renovation Reveal: Before and After
Over the past few weeks we’ve made big strides on our master bathroom and closet, and the space finally feels functional. We’re close to the finish line — enough that we can truly enjoy the upgrades: a double sink (our very first), my favorite toilet, and a real closet system instead of a few hanging bars. It’s a dramatic improvement and honestly feels like a small victory dance every time we walk in.
This renovation has stretched longer than we originally planned (don’t they all?), but we’re thrilled with the progress. We’ve shared sneak peeks on our Instagram Stories, and now we wanted to give a fuller update with photos we took this morning to show where things stand.

Shortly after Thanksgiving we had the shower tile finished and had started the floor tile with plans to grout both at once. Then our plumber scheduled knee surgery with only a few days’ notice and would be out for five weeks. That created a hard deadline: if we wanted fixtures installed before February we had to get the basic room ready fast.
We regrouped quickly and prioritized getting the floor fully tiled and grouted so the vanity, toilet, and tub could be set on top of it. That meant the shower would take a back seat for a bit, but getting a functioning sink and toilet back was the priority — no more nightly trips to the hall bathroom.
Another practical benefit: installing wall molding would be much easier before the fixtures were in place. So we focused on the trim, tiled, grouted, caulked, and painted in a concentrated push — a blur of late nights totaling about 40 hours — and finished just in time. (We’ll share a separate post on the thick trim we installed; it’s one of our favorite choices and elevates the room.)
Even though we finished the prep work before the plumber’s surgery, he ultimately couldn’t fit us in on his last available day. The good news was that he sent two colleagues the next day to complete the installations — which beat waiting five weeks. They weren’t able to bring the tub kit that day, so the tub install remains pending along with final shower trimming once we grout and seal the shower.

So the bathroom is looking lovely but still has an uninstalled tub and an ungrouted shower — the tub is currently sitting in our bedroom waiting for its turn. Even so, we’re thrilled to have running faucets and a flushing toilet again. That alone has lifted a lot of stress.

A few readers asked why we didn’t install the toilet and vanity ourselves. While we’re capable of those tasks, we preferred the plumber to finish the job so he could stand behind all of the work — including the new pipes within the walls. Having a licensed pro complete the plumbing helps with warranty and code-related issues on a big gut renovation, and avoids ambiguity about responsibility if a leak appears later.

Once the toilet and sink were functional, we pivoted to another high-priority area: the closet. With holiday guests on the way we needed to reclaim the dining room and garage from piles of displaced clothing and boxed parts. Over a few days around Christmas we installed an Ikea Pax system and trimmed it out to feel built-in. It was so satisfying to move our clothes back into a proper closet and clear the dining table for guests.

We picked a secondhand Turkish rug on Etsy that adds warmth and a slightly faded, layered look. It works beautifully in front of the vanity and also anchors the closet — it’s one of those small touches that makes the space feel finished even while a few big items remain undone.

We also hung the new mirrors, mounted an arched mirror in the closet, installed a capiz chandelier, and added greenery and woven baskets to bring texture and life into the rooms. Those decorative choices gave us a morale boost and made the spaces feel welcoming, even as finishing tasks remain.
Here’s what’s left on our to-do list — a short, realistic list compared to the long one we started with:
- Wire the vanity fixtures: We installed the fixtures but held off on wiring until we chose the final finish. I’ll share an InstaStory showing the options and why we picked the winner.
- Paint the vanity: We like the current gray but are considering a softer, muted green to warm the room. Still deciding.
- Hang towel hooks & art: Plan to install a mix of hooks and artwork above the tub and over the toilet; tub installation comes first.
- Choose and hang a shower curtain: We’re leaning toward a fabric curtain for softness and easier maintenance versus a glass door. We may add glass later if needed.
- Install and frost the bathroom door: The 15-light glass door we ordered should arrive soon; we’ll hang it and apply frosted film for privacy.
We’ll share a full budget breakdown and a complete reveal when the project is finished. So far the renovation has been straightforward with no major surprises behind the walls, which we’re grateful for.
P.S. If you want to catch up on the earlier posts about this remodel, check out our first post with a before tour and the planning post that walks through the floor plan and tile choices.